Design, Procurement, Construction, Installation, Testing, Commissioning, Trial Run of 3 months, and 5-year O&M of:

  • 14 Intermediate Effluent Pumping stations

  • 1 Terminal Pumping station

  • 20 MLD Common Effluent Treatment Plant

  • RO reject disposal pipeline (12 MLD) from RO reject tank to outfall at Sukhbhadar creek

  • Master Balancing Reservoir – Recycled water (20 MLD)

  • Pumping station for Recycled water (80 MLD)

  • Contractor: M/s Larsen & Toubro Ltd

  • Contract Value (INR Crores): ₹156.86

  • Status: Ongoing