Design, Procurement, Construction, Installation, Testing, and Commissioning. Includes a 3-month trial run and 5-year O&M of:
-
6 Intermediate Sewage Pumping Stations
-
1 Terminal Pumping Station
-
10 MLD Sewage Treatment Plant
-
7.5 MLD Master Balancing Reservoir
-
70 MLD Pumping Station
-
Contractor: M/s Larsen & Toubro Ltd
-
Contract Value (INR Crores): ₹53.13
-
Status: Ongoing